Tampa Bay Construction Cost Index

What component-level construction work costs in Tampa Bay right now, by trade cluster: aggregated bare-cost ranges from the same current cost data our estimating engine prices jobs from, refreshed quarterly. Cite it, link it, argue with it. It carries its date.

Cost levels by trade

Bare-cost ranges, July 2026

Tampa Bay construction bare-cost ranges by trade cluster, July 2026
Trade clusterUnitBookLow (p25)MedianHigh (p75)Rows
Concrete slab workper SFnew construction$1.15$2.04$5.5375
Wall, floor, and roof framingper SFnew construction$1.07$1.43$1.7214
Insulationper SFnew construction$0.44$1.62$4.5312
Drywall and gypsum workper SFrenovation$0.85$3.49$4.4422
Interior wall and ceiling paintingper SFrenovation$4.20$5.03$5.7810
Ceramic tile workper SFrenovation$0.65$1.56$4.1043
Bathroom fixture work itemsper fixture taskrenovation$29.20$56.05$82.7856
Outlets, switches, and devicesper devicerenovation$31.70$62.50$11135
Floor covering workper SFrenovation$0.44$0.88$2.8830
Shingle roofing (tear-off and replace tasks)per square (100 SF)renovation$325$436$55669

Figures are percentile aggregates (25th, median, 75th) over component-level material and labor cost rows in the current Craftsman 2026 cost data, computed July 2026 and refreshed quarterly. They are bare costs: material plus labor for individual work items, before contractor overhead and profit, and before job-specific conditions. They are not installed project totals and not bids. A typical Tampa Bay bid adds 25% or more on top of bare cost. Local figures apply the same ZIP3 area modifiers the estimating engine uses.

Geography

The ZIP-level modifiers that localize the index

Tampa Bay ZIP3 area cost modifiers
ZIP3Areavs national baseline
335Tampabaseline
336Tampabaseline
337St Petersburg / Clearwater-5%
338Lakeland-7%
342Bradenton-5%

The spread matters: the same scope priced in Lakeland lands about 7% below the identical scope in Tampa proper. Estimates that ignore intra-metro geography start wrong before the first line is priced.

Frequently asked

About the index

What is the Tampa Bay Construction Cost Index?
A quarterly, first-party snapshot of component-level bare construction costs for the Tampa Bay area, aggregated from the current Craftsman 2026 cost data our estimating engine prices from. It tracks cost levels by trade cluster and the ZIP-level modifiers that localize them.
Are these numbers what a contractor will bid?
No. They are bare costs: material plus labor for component-level work items, before contractor overhead and profit. A typical Tampa Bay bid adds 25% or more on top of bare cost.
How often does the index refresh?
Quarterly, with the as-of date printed on the page. Figures are aggregates (25th percentile, median, 75th percentile) over the underlying cost rows, never the raw licensed data itself.

Estimate from the data behind this index.